Fundamentals of Power Boiler Blowoff Systems


Release Date: May 7, 2026
Delivery: Online
Code Version:  2025
Presentation Style: Documentary
Approximate Time:  3 hours

Continuing Education Qualification: IS CommissionO Endorsement, PEI Inservice
Education Partner for Credential Renewal: API 510

Synopsis: This course steps learners through what boiler blowoff is and why it is performed. The difference between blowoff and blowdown and other related terminology begins the training, followed by more detailed information on how surface blowdown and bottom blowoff are performed, and the components used to perform these procedures, such as valves, piping, and skimmers.

Next learners are introduced to ASME BPV Code and NBIC requirements for blowdown and blowoff systems, valves and piping. The National Board publication NB-27, Guide to Blowoff Vessels is reviewed, specifically looking at blowoff tanks and separators. The course concludes with learning about blowoff tank sizing and vent design.

General Info General
Register for Training Enroll Now! - $75.00
Course Information General Information

 

Fundamentals of Power Boiler Blowoff Systems steps learners through what boiler blowoff is and why it is performed. The difference between blowoff and blowdown and other related terminology begins the training, followed by more detailed information on how surface blowdown and bottom blowoff are performed, and the components used to perform these procedures, such as valves, piping, and skimmers.

Next learners are introduced to ASME BPV Code and NBIC requirements for blowdown and blowoff systems, valves and piping. The National Board publication NB-27, Guide to Blowoff Vessels is reviewed, specifically looking at blowoff tanks and separators. The course concludes with learning about blowoff tank sizing and vent design.

Learning Outcomes
After completing this course, students will be able to:  

  • Properly use the terms blowoff and blowdown .
  • Explain Code requirements for surface blowdown.
  • Explain Code requirements for bottom blowoff.
  • Describe blowoff valve requirements.
  • Describe piping requirements.
  • Explain flow phenomena in blowoff piping, such as steam flashing and water hammer.
  • Understand the contents of the National Board Guide for Blowoff Vessels (NB-27).

Reference Materials
Although not required, each student may find it helpful to have the following materials (currently mandated edition):

  • ASME Section I,  Rules for Construction of Power Boilers
  • ASME B31.1-1-2022, Power Piping
  • National Board Inspection Code (NBIC), Part 1, Installation
  • National Board Publication, NB-27, Guide for Blowoff Vessels

Note: ASME Code and Standards may be ordered through the ASME website.

Criteria for Successful Completion
As a minimum, for a National Board Certificate of Completion to be issued, students must:

  • actively participate in all online course interactions
  • respond to all knowledge check questions